Difference between revisions of "Facilities/Priority List"

From Makers Local 256
Jump to: navigation, search
(Textiles Migration: updating with latest plan)
(Textiles Migration: adding potential plan a for expanding fab lab)
Line 2: Line 2:
  
 
=== Textiles Migration ===
 
=== Textiles Migration ===
 +
==== Potential Plan A ====
 +
# Move equipment from Tool area next to existing fab lab wall
 +
## Disperse unused shop property from left most shelving unit next to metal supply
 +
## Break down left most shelving unit into scrap, or put on street
 +
## Build a work table for the tabletop CNC to go on
 +
## Move lockers to next to new work table
 +
# Take out module of sawdust collection unit that is run into that area.
 +
# Move fab lab wall to first wooden post.  Not the wooden post closest to the radial arm saw.
 +
#* Moving it farther than this post would require a relocation of the electrical box. 
 +
# Build new wall.  Only entrance to area will be from existing fab lab door.
 +
# Break down textiles table, re-assemble inside newly expanded room
 +
# Build shelves or bring in narrow tables for sewing machines to be placed.
 +
# Move textiles equipment into new room
 +
==== Additional Info ====
 
* Location
 
* Location
 
** The Fab Lab will be expanded to accommodate the textiles area.  A plan for how this will be accomplished will be set on Tuesday May 2nd, 2017 @ 6pm
 
** The Fab Lab will be expanded to accommodate the textiles area.  A plan for how this will be accomplished will be set on Tuesday May 2nd, 2017 @ 6pm

Revision as of 14:51, 22 April 2017

Doing

Textiles Migration

Potential Plan A

  1. Move equipment from Tool area next to existing fab lab wall
    1. Disperse unused shop property from left most shelving unit next to metal supply
    2. Break down left most shelving unit into scrap, or put on street
    3. Build a work table for the tabletop CNC to go on
    4. Move lockers to next to new work table
  2. Take out module of sawdust collection unit that is run into that area.
  3. Move fab lab wall to first wooden post. Not the wooden post closest to the radial arm saw.
    • Moving it farther than this post would require a relocation of the electrical box.
  4. Build new wall. Only entrance to area will be from existing fab lab door.
  5. Break down textiles table, re-assemble inside newly expanded room
  6. Build shelves or bring in narrow tables for sewing machines to be placed.
  7. Move textiles equipment into new room

Additional Info

  • Location
    • The Fab Lab will be expanded to accommodate the textiles area. A plan for how this will be accomplished will be set on Tuesday May 2nd, 2017 @ 6pm
    • Topics to consider:
      • Where will the existing inventory and tools in that area be moved to. Phil had a suggestion of moving the existing shelving unit alongside the car port and building work tables to hold the equipment and items.
      • Is there electricity in this area for the textiles machines.
      • Will the sawdust collection unit have to be modified.
      • Will there be a second entrace? Can it be added later?
  • Funding and Materials
    • Jeff is fronting $300 of risk money and will ask for reimbursement at a later time.
    • Lumber is currently being stored in the A/V area.
  • Work Day(s)
    • Tuesday May 6th @ 6pm will be the planning meeting
    • Sunday May 7th will be the first work day for this effort

To Do

  • ELECTRICAL
    • Tools area breakers
    • AV area wiring clusterfuck
    • Outlets that need attention
      • Kitchen switch and outlet
      • Hallway bathroom
      • Office bathroom
      • Front door
  • UNISTRUT
    • Install Unistrut for Radio Mast Mount \ Camera Mount
    • To be installed either on the corner of the building, or if that is not feasable, behind member storage.
    • Ctag and Omegix to install on 2016.05.21 (Cleanup Day)
  • MEGADOOR
    • New exterior usb port on door.
    • usb/nfc auth on back door.
    • Fix front door wiring
  • Set up consumables tracking.
    • Item "Stock" for shop?
    • Items that should always be available (soap, duct tape) are voted on by the membership, and then facilities committee works to keep them in stock.
  • VENDING
    • LED matrix in soda machine
    • other vending machine Qt interface
    • Other vending machine item supply
  • UPGRAYEDS
    • Install water heater timer
    • [doing] Renovate bathroom
      • New linoleum floor
      • CNC new sink cabinet
      • Better fan? Connect fan to outside exhaust?
  • Drywall (+ artwork) around upstairs banister
  • Replace bikeshed
  • Ceiling fan blades in office.
  • Traction tape on stairs.
  • opening office window.
  • FABLAB
    • Finish installing ceiling.
    • Install shelving.
    • [done] fablab AC
      • Thanks Travis!
  • [done] Organize lost and found
    • Four shelves. Four weeks.
      • Three weeks to collect item.
      • fourth week anyone can take it.
      • End of the fourth week item is tossed.
    • All incoming/outgoing items are cataloged.
  • FIRST AID
    • [doing] Move main first aid kit out of bathroom.
    • Provide floorplan of safety equipment
    • Provide on-demand lectures for first aid.
  • Shop tours? Field trips?
    • The shop -- as a nonprofit with the stated goal of spreading the maker spirit -- should be an amazing place for school field trips. Currently I actively avoid them, because there's no way to guarantee that the kids don't encounter a drunk member in the shop. Fixing the problem then censors members in the name of making the shop kid-friendly, which it isn't.
    • I think a solution to this dilemma would be to schedule field trips, and then alert the shop that there will be a dry day when no alcohol consumption or obscenity will be tolerated.
  • BIKESHED
    • Bikeshedding
      • Shasta?
    • Bikeshed

Done

Bathroom Renovation

Dimensions

Environment:

  • Bathroom floor
    • 6' x 5'
  • Horizontal Trim
    • 36 & 1/4" from floor

Old Vanity:

  • Existing Vanity
    • front: 24" x 30"
  • Footwell
    • 4" x 4"

New Vanity:

  • Plywood
    • 5/16" thick
  • New Countertop
    • 28" x 25" (w x d)
    • 5" tall at rear panel
    • 1&1/2" tall at front lip
    • 3/4" thick at middle section
  • New Vanity Frame
    • (36.25 - 5) = 31.25" tall
    • 27.5" wide
    • 23.5" deep
  • Footwell
    • 4" x 4"

Supplies

  • [HAVE - Norm] Countertop
  • Floor Tiles ($0.69 per ft^2)
  • Adhesive ($13.47 per gallon)
  • Rubber Trim ($69.97)
    • 4" tall, 120' long
  • Glue for Trim ($4.97)
    • Probably need two
  • Sealer ($15.87 per gallon)
  • High Efficiency Toilet ($100)
  • Wall Paint ($???)
  • Drywall ($12)

Estimated Total Cost: $243

Stair Treads

Shop has 13 stairs. Need 13 treads.

Stairs are 32" x 9"

A pack of 12 traction tape pieces is on the way.