# Summer Appreciation - Making the shop enjoyable through the summer heat. Looking at ECD 5/11.
+
== Doing ==
## Installing A/Cs
+
 
## Weatherization
+
== To Do ==
# Organization - Looking to get one done a month.
+
 
## Cleaning & Preparing Equipment Room
+
* ELECTRICAL
## Adding More Storage
+
** Tools area breakers
## Cleaning & Preparing Library
+
** AV area wiring clusterfuck
# Shop Safety - We already have some basic gear down, looking at getting one done each month in parallel with 'Organization'.
+
** Outlets that need attention
## Mount additional fire extinguishers & emergency flashlights; two more in Main Room, one in each other major area.
+
*** Kitchen switch and outlet
## Place Emergency Evacuation placards; fire and tornado.
+
*** Hallway bathroom
 +
*** Office bathroom
 +
*** Front door
 +
 
 +
* PNEUMATIC
 +
** Replace leaking hose above 2nd floor CNC Machine
 +
** Get on-demand ventilation for 3-D printers
 +
 
 +
 
 +
* Set up consumables tracking.
 +
** Item "Stock" for shop?
 +
** Items that should always be available (soap, duct tape) are voted on by the membership, and then facilities committee works to keep them in stock.
 +
 
 +
* UPGRAYEDS
 +
** Install water heater timer
 +
** Drywall (+ artwork) around upstairs banister
 +
** Replace bikeshed
 +
** opening office window.
 +
 
 +
* FIRST AID
 +
** [doing] Move main first aid kit out of bathroom.
 +
** Provide floorplan of safety equipment
 +
** Provide on-demand lectures for first aid.
 +
 
 +
* Shop tours? Field trips?
 +
** The shop -- as a nonprofit with the stated goal of spreading the maker spirit -- should be an amazing place for school field trips. Currently I actively avoid them, because there's no way to guarantee that the kids don't encounter a drunk member in the shop. Fixing the problem then censors members in the name of making the shop kid-friendly, which it isn't.
 +
** I think a solution to this dilemma would be to schedule field trips, and then alert the shop that there will be a dry day when no alcohol consumption or obscenity will be tolerated.
 +
 
 +
== Done ==
 +
 
 +
* [[Facilities/Priority_List/Textiles Migration | Textiles Migration]]
 +
 
 +
* Renovate bathroom
 +
** New linoleum floor
 +
** CNC new sink cabinet
 +
** Better fan? Connect fan to outside exhaust?
 +
 
 +
* UNISTRUT
 +
** Install Unistrut for Radio Mast Mount \ Camera Mount
 +
** To be installed either on the corner of the building, or if that is not feasable, behind member storage.
 +
** Ctag and Omegix to install on 2016.05.21 (Cleanup Day)
 +
 
 +
* FABLAB
 +
** Finish installing ceiling.
 +
** Install shelving.
 +
** [done] fablab AC
 +
*** Thanks Travis!
 +
 
 +
* Organize lost and found
 +
** Four shelves. Four weeks.
 +
*** Three weeks to collect item.
 +
*** fourth week anyone can take it.
 +
*** End of the fourth week item is tossed.
 +
** All incoming/outgoing items are cataloged.
 +
 
 +
=== Bathroom Renovation ===
 +
 
 +
==== Dimensions ====
 +
 
 +
Environment:
 +
* Bathroom floor
 +
** 6' x 5'
 +
* Horizontal Trim
 +
** 36 & 1/4" from floor
 +
 
 +
Old Vanity:
 +
* Existing Vanity
 +
** front: 24" x 30"
 +
* Footwell
 +
** 4" x 4"
 +
 
 +
New Vanity:
 +
* Plywood
 +
** 5/16" thick
 +
* New Countertop
 +
** 28" x 25" (w x d)
 +
** 5" tall at rear panel
 +
** 1&1/2" tall at front lip
 +
** 3/4" thick at middle section
 +
* New Vanity Frame
 +
** (36.25 - 5) = 31.25" tall
 +
** 27.5" wide
 +
** 23.5" deep
 +
* Footwell
 +
** 4" x 4"
 +
 
 +
==== Supplies ====
 +
 
 +
* [HAVE - Norm] Countertop
 +
* Floor Tiles ($0.69 per ft^2)
 +
* Adhesive ($13.47 per gallon)
 +
* Rubber Trim ($69.97)
 +
** 4" tall, 120' long
 +
* Glue for Trim ($4.97)
 +
** Probably need two
 +
* Sealer ($15.87 per gallon)
 +
* High Efficiency Toilet ($100)
 +
* Wall Paint ($???)
 +
* Drywall ($12)
 +
 
 +
Estimated Total Cost: $243
 +
 
 +
 
 +
[[Category:Facilities]]

Latest revision as of 19:59, 17 March 2024

Doing

To Do

  • ELECTRICAL
    • Tools area breakers
    • AV area wiring clusterfuck
    • Outlets that need attention
      • Kitchen switch and outlet
      • Hallway bathroom
      • Office bathroom
      • Front door
  • PNEUMATIC
    • Replace leaking hose above 2nd floor CNC Machine
    • Get on-demand ventilation for 3-D printers


  • Set up consumables tracking.
    • Item "Stock" for shop?
    • Items that should always be available (soap, duct tape) are voted on by the membership, and then facilities committee works to keep them in stock.
  • UPGRAYEDS
    • Install water heater timer
    • Drywall (+ artwork) around upstairs banister
    • Replace bikeshed
    • opening office window.
  • FIRST AID
    • [doing] Move main first aid kit out of bathroom.
    • Provide floorplan of safety equipment
    • Provide on-demand lectures for first aid.
  • Shop tours? Field trips?
    • The shop -- as a nonprofit with the stated goal of spreading the maker spirit -- should be an amazing place for school field trips. Currently I actively avoid them, because there's no way to guarantee that the kids don't encounter a drunk member in the shop. Fixing the problem then censors members in the name of making the shop kid-friendly, which it isn't.
    • I think a solution to this dilemma would be to schedule field trips, and then alert the shop that there will be a dry day when no alcohol consumption or obscenity will be tolerated.

Done

  • Renovate bathroom
    • New linoleum floor
    • CNC new sink cabinet
    • Better fan? Connect fan to outside exhaust?
  • UNISTRUT
    • Install Unistrut for Radio Mast Mount \ Camera Mount
    • To be installed either on the corner of the building, or if that is not feasable, behind member storage.
    • Ctag and Omegix to install on 2016.05.21 (Cleanup Day)
  • FABLAB
    • Finish installing ceiling.
    • Install shelving.
    • [done] fablab AC
      • Thanks Travis!
  • Organize lost and found
    • Four shelves. Four weeks.
      • Three weeks to collect item.
      • fourth week anyone can take it.
      • End of the fourth week item is tossed.
    • All incoming/outgoing items are cataloged.

Bathroom Renovation

Dimensions

Environment:

  • Bathroom floor
    • 6' x 5'
  • Horizontal Trim
    • 36 & 1/4" from floor

Old Vanity:

  • Existing Vanity
    • front: 24" x 30"
  • Footwell
    • 4" x 4"

New Vanity:

  • Plywood
    • 5/16" thick
  • New Countertop
    • 28" x 25" (w x d)
    • 5" tall at rear panel
    • 1&1/2" tall at front lip
    • 3/4" thick at middle section
  • New Vanity Frame
    • (36.25 - 5) = 31.25" tall
    • 27.5" wide
    • 23.5" deep
  • Footwell
    • 4" x 4"

Supplies

  • [HAVE - Norm] Countertop
  • Floor Tiles ($0.69 per ft^2)
  • Adhesive ($13.47 per gallon)
  • Rubber Trim ($69.97)
    • 4" tall, 120' long
  • Glue for Trim ($4.97)
    • Probably need two
  • Sealer ($15.87 per gallon)
  • High Efficiency Toilet ($100)
  • Wall Paint ($???)
  • Drywall ($12)

Estimated Total Cost: $243